Production Adjustments at Domestic Bases due to the Spread of COVID-19
April 7, 2020
The Hitachi Construction Machinery Group plans to gradually adjust production in 4 domestic plants from April to May for integrated production, assembly, and painting as shown below, in light of the decline in demand worldwide due to the spread of COVID-19.
Going forward, the Hitachi Construction Machinery Group will review its production plans as necessary, depending on the tightening of regulations by governments in each country or region.
The spread of COVID-19 and their prolonged duration are having an impact on the lives of people around the world. The entire group will work together to help prevent the spread of COVID-19 from spreading and resolve the confusion.
■ Tsuchiura Works (Tsuchiura-shi, Ibaraki)
Production adjustment period: April 13 to April 17, May 11 to May 15
Production adjustment items: Medium hydraulic excavators
■ Ryugasaki Works (Ryugasaki-shi, Ibaraki)
Production adjustment period: April 13 to April 17, May 11 to May 15
Production adjustment items: Medium wheel loaders
■ Kasumigaura Works (Kasumigaura-shi, Ibaraki)
Production adjustment period: April 13 to April 17, May 11 to May 15
Production adjustment items: Components of hydraulic equipment (driving motors, reduction gears, etc.)
■ Hitachinaka-Rinko Works (Hitachinaka-shi, Ibaraki)
Production adjustment period: April 14 to April 20, May 11 to May 15
Production adjustment items: Large hydraulic excavators